Interstate 4 construction work sped up due to COVID-19 traffic lull

Sections of the massive Interstate 4 “Ultimate” project in Central Florida will see accelerated work as the state takes advantage of a coronavirus-created reduction in traffic.

Gov. Ron DeSantis and Department of Transportation Secretary Kevin Thibault said Saturday that work will be moved up a month or two on parts of the 21-mile project in Seminole and Orange counties.

“We should take advantage of this pause,” DeSantis said. “People aren’t able to go to work. Kids aren’t going to school. There’s a lot of negatives involved. The fact that we don’t have as many people on the roads, let’s take advantage of that and try to make some progress.”

The $2.3 billion project is more than 250 days behind schedule.

RELATED Coronavirus 'stay-at-home' order; What is essential business

On April 1, the state announced that about $2.1 billion in other road projects from Key West to the Panhandle were being moved up by weeks or months as traffic on many heavily traveled roads had become a “trickle,” with jobless claims spiking and most of the hospitality industry shutting down or scaling back because of COVID-19, the respiratory disease caused by the coronavirus.

The I-4 project, currently on a path for completion in late 2021, will see additional daytime lane closures. Traffic that had been between 100,000 and 120,000 vehicles a day in areas is down to 40,000 a day, Thibault said.

The work being advanced will include portions of westbound I-4 starting at the State Road 434 interchange at Longwood and part of the State Road 408 interchange.

DeSantis said the work won’t increase the cost of the project, which ultimately is hoped to relieve traffic on one of the state’s most-congested highways.

Thibault said the goal is to complete the State Road 408 interchange work, which is designed to ease a major traffic bottleneck, by Independence Day.

“We’re trying to get things done so that when normalcy returns (after the COVID-19 outbreak subsides), everybody getting back, the normalcy can also happen as part of the roadways,” Thibault said.

Among the projects previously identified included construction of a new Howard Frankland Bridge that links Hillsborough and Pinellas counties, widening Southern Boulevard in western Palm Beach County, construction on the U.S. 1 Cow Key Bridge at Key West, widening State Road 951 in southern Collier County, and the 23rd Street Flyover project at the intersection of U.S. 98 and 23rd Street in Bay County.

Thibault said the need for physical distancing to slow the spread of the virus also isn’t hampering progress on planning for other projects, such as three new or expanded toll roads stretching from Collier County to the Georgia border.

“Fortunately, we’ve been able to do everything to keep the projects going, the engineering community for the most part can do their things virtually,” Thibault said, adding, "We are on the cusp of actually doing 3-D design in our engineering plans. So, they’re able to continue to develop projects and move those projects forward, even in this world.”

MAP: Florida coronavirus cases by county

If you feel sick:

The Florida Department of Health has opened a COVID-19 Call Center at 1-866-779-6121. Agents will answer questions around the clock. Questions may also be emailed to covid-19@flhealth.gov. Email responses will be sent during call center hours.

LINK: Florida's COVID-19 website

CORONAVIRUS IN FLORIDA: What you need to know

AROUND THE WORLD: CoronavirusNOW.com

Map of known COVID-19 cases:

MOBILE APP USERS: Click here for map